Campus Development

  • Phase 1: Redevelopment of Block E

    The construction of new staircase of Block H was completed at the end of April 2017. The Opening Ceremony will be held on 6th July 2017 (Thursday) at 2pm at Munsang College.

    The demolition of Block E commenced in June 2017 and the noisy works of Contract 2 will commence in July 2017 during the summer holiday.


    The tender interview of Contract 2 (Redevelopment of Block E) was successfully held on 11th May 2017 (Thursday). Representatives of eight construction companies came for an interview. Architectural consultants and sub-consultants of AD+RG, and representatives of Munsang College conducted the tender interview together.

  • Phase 2: Construction of New Assembly Hall

    Meeting with EDB officers was held on 21st April 2017 at Munsang College. Architectural consultants of Percy Thomas Partnership (HK) Limited and representatives of Munsang College were present. The meeting allowed our school to appeal for the urgent necessity of obtaining a new school hall for our students due to a lack of available facilities for conducting various Other Learning Experience activities and meaningful educational initiatives. Application for Capital Works Resource Allocation Exercise (CWRAE) would be submitted at the end of June 2017.

  • Legislative Council

    Finance Committee Meeting on Friday, 14 December 2018


    Public Works Subcommittee (7 November 2018)


    Education Panel (11 May 2018)